On December 15, 2019, in the 1.25 million tons/year ethane cracking ethylene plant of the Lianyungang Petrochemical Large-scale Equipment Hoisting Project Department, the quench tower with a total weight of 855 tons was hoisted on XCMG XGC28000 (2000 tons) crawler crane and 650 tons crawler. With the cooperation of cranes, it was successfully hoisted in place, and the first show of the 2000-ton crawler crane in Lianyungang was successfully completed.
The quenching tower hoisting is the first hoisting of Lianyungang Petrochemical's large and heavy equipment, and it is also a new starting point for the new Lianyungang Petrochemical plant. The full cooperation of all participating units has ensured the control point of this large-scale equipment hoisting and established the smooth progress of the entire project "Head work". This hoisting is a new starting point for Lianyungang Petrochemical, as well as a new start for the company's Lianyungang project department's large equipment hoisting.